Project Status, Feb. 20 [1]
Activities Completed This Week:
- Design Document completed
- Planning and preparation for onsite next week
- Review of ExactTarget data extension solution
- Community design review
- Schedule of event management tool demos
Activities Planned for Next Week:
- Submit design document
- Onsite meetings scheduled
- Review and finalize data model
- Review and finalize remaining project schedule
- Review and finalize data integration requirements and transformation needs
- Review security
- Begin Salesforce Build