With the end of the calendar year fast approaching, and all four campuses and the System office closing from December 26th through January 2nd, we wanted to provide critical dates on submitting requisitions, payment processing and other requests.
Due to ongoing supply chain disruptions, escalating prices, and the labor market affecting both suppliers and the University of Colorado, the Procurement Service Center is extending the January 21, 2022 Procurement Declaration through December 31, 2022.
Due to ongoing supply chain disruptions, escalating prices, and the labor market affecting both suppliers and the University of Colorado, the Procurement Service Center is extending the January 21, 2022 Procurement Declaration through November 30, 2022.
We know contracting through the PSC is now taking longer than in the past. There are several causes for extended timelines, many of which are common among entities throughout the economy, including staffing shortages throughout the supply chain, risk evaluations, and changing attitudes among our suppliers. While we are working hard to address these constraints, it’s important to make you aware of our current cycle time estimates and how together, we can improve them.